Cost

The costs to implement a transit signal priority demonstration project in Los Angeles, California was $10 million.


January 2001
Los Angeles,California,United States


Summary Information

The Los Angeles DOT (LADOT) implemented a $10 million bus signal priority demonstration project along two corridors (Ventura Boulevard and the Santa Monica-Beverly Hills- Montebello route) in the City of Los Angeles, California. The initial deployment began in June 2000. The system consists of 331 loop detectors, 210 intersections equipped with automatic vehicle identification (AVI) sensors at the controller cabinet, and 150 transponder-equipped buses, and central control system software. Loop detection technology is used to detect the presence of a bus approaching the intersection. The bus identification is detected by the AVI sensor and sent to the transit management computer located at the LADOT transportation management center. The system checks the bus' schedule and headway to determine if it is early or on time. If the bus is behind schedule, one of four types of priority modes is granted. Loop detection was selected as the most reliable, accurate, and cost-effective detection technology, over radio-frequency antenna transponder detection and infrared beacon system. The cost per signalized intersection included an average of equipment (roadway and at intersection), and software costs.

See Also:

Chada, Shireen and Robert Newland, Effectiveness of Bus Signal Priority: Final Report, Prepared for the Florida DOT and USDOT by the University of South Florida (CTR-416-04). January 2002.


System Cost Comments

No comments posted to date

Comment on this System Cost

To comment on this summary, fill in the information below and click on submit. An asterisk (*) indicates a required field. Your name and email address, if provided, will not be posted, but are to contact you, if needed to clarify your comments.



Source

Implementing Smart Transit Priority System for Metro Rapid Bus in Los Angeles

Author: Hu, Kang, and Sean Skehan (City of Los Angeles, Department of Transportation), and Rex Gephart (Los Angeles County Metropolitan Transportation Authority)

Correspondence with primary author March 2001.

Published By: Paper presented at the 80th Annual Transportation Research Board Meeting

Source Date: January 2001


System Cost

Average cost: $13,500 per signalized intersection (2000).

Transponder cost: Approximately $75 per bus (2000).