Emergency Management (15 unique system cost summaries found)
Commercially available, off-the-shelf technology that enhances the safety and security of hazmat transportation operations ranges in cost from $250 to $3,500 per vehicle.(31 August 2004)
Commercially available, off-the-shelf technology that enhances the safety and security of hazmat transportation operations ranges in cost from $250 to $3,500 per vehicle.(31 August 2004)
The capital cost to design, develop, test, and integrate ACN dispatch center equipment and software was estimated at $152,400.(February 2001)
The annualized life-cycle costs for full ITS deployment and operations in Tucson were estimated at $72.1 million. (May 2005)
A modeling study evaluated the potential deployment of full ITS capabilities in Cincinnati. The annualized life-cycle cost was estimated at $98.2 million.(May 2005)
The annualized life-cycle costs for full ITS deployment and operations in Seattle were estimated at $132.1 million.(May 2005)
Over half of the $3.25 million cost for the San Antonio Lifelink advanced telemedicine project was attributed to reseach and development.(May 2000)
Louisiana deployed seven flood detection and traffic evacuation monitoring stations for approximately $200,000.(11/1/2003)
The Pennsylvania (PA) Turnpike Commission expanded its statewide advanced traveler information system (ATIS) to better inform motorists of traffic, weather, and emergency conditions along the PA Turnpike. The overall project cost was $8.2 million.(April 2006)
The annualized life-cycle costs for full ITS deployment and operations in Tucson were estimated at $72.1 million. (May 2005)
A modeling study evaluated the potential deployment of full ITS capabilities in Cincinnati. The annualized life-cycle cost was estimated at $98.2 million.(May 2005)
The annualized life-cycle costs for full ITS deployment and operations in Seattle were estimated at $132.1 million.(May 2005)
TMC central hardware costs can exceed $200,000 if regional communications and system integration are required.(5 August 2004)
Emergency preemption equipment was deployed at several intersections in British Columbia, Canada at a cost of $4,000 (Canadian) per intersection.(November 2001)
A GPS-based satellite system costing roughly $4,000 per intersection and $2,000 per vehicle, allows Palm Beach County, Florida fire personnel to responder faster.(1 June 1997)
TMC central hardware costs can exceed $200,000 if regional communications and system integration are required.(5 August 2004)
The cost of O&M at the Arizona TMC was estimated at $2 million per year.(January 2006)
In Michigan, the Flint Mass Transportation Authority budgeted $1 million to develop a central system for county-wide AVL.(June 2005)
The annualized life-cycle costs for full ITS deployment and operations in Tucson were estimated at $72.1 million. (May 2005)
A modeling study evaluated the potential deployment of full ITS capabilities in Cincinnati. The annualized life-cycle cost was estimated at $98.2 million.(May 2005)
The annualized life-cycle costs for full ITS deployment and operations in Seattle were estimated at $132.1 million.(May 2005)
The cost to design and deploy a shared regional transportation, emergency, and communications center in Austin and Travis Counties (Texas) was estimated at $5 million.(May 2004)
The total capital cost of the Seattle MMDI emergency operations centers project including equipment and planning/development costs were $151,700; O&M costs were approximately 5% of the equipment costs.(30 May 2000)
A GPS-based satellite system costing roughly $4,000 per intersection and $2,000 per vehicle, allows Palm Beach County, Florida fire personnel to responder faster.(1 June 1997)