Equipment Costs for Roadside Rail Crossing (R-RC)
Note: The date in parentheses under the capital cost value and O&M cost value represents the dollar year of the cost values. All costs are in $K.
| Unit Cost Element |
IDAS # |
Life Years |
Capital Cost $K (Source Year) |
O&M Cost $K/year (Source Year) |
Description |
| Rail Crossing 4-Quad Gate, Signals | RS021 | 20 | 115.0 - 130.0 (1995) | 4.25 - 4.85 (1995) | Gates and signals. |
| Rail Crossing Train Detector | RS022 | 20 | 16.0 - 21.5 (1995) | 0.77 - 1.03 (1995) | Train detector circuitry and communication line from intelligent interface controller (IIC) to wayside interface equipment (WIE). Assume two track crossing with two 0.5 mile communication lines. |
| Rail Crossing Controller | RS023 | 10 | 8.0 - 10.0 (1995) | 0.4 - 0.5 (1995) | Intelligent interface controller (IIC). |
| Rail Crossing Pedestrian Warning Signal, Gates | RS024 | 20 | 10.0 - 15.0 (1995) | 0.2 - 0.3 (1995) | Pedestrian warning signal and gates. |
| Rail Crossing Trapped Vehicle Detector | RS025 | 10 | 25.0 - 30.0 (1995) | 1.25 - 1.50 (1995) | Entrapped vehicle detection camera, with poles and controller. |