Unit Costs (Unadjusted) (View Adjusted)

Equipment Costs for Transit Management Center (TR)

Note: The date in parentheses under the capital cost value and O&M cost value represents the dollar year of the cost values. All costs are in $K.

Unit Cost Element IDAS # Life
Years
Capital Cost
$K
(Source Year)
O&M Cost
$K/year
(Source Year)
Description
Basic Facilities, Comm. for Large AreaTR0144000
(1995)
400 - 600
(1995)
For population >750,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm. for Medium AreaTR0153200
(1995)
400 - 480
(1995)
For population <750,000 and >250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Basic Facilities, Comm. for Small AreaTR0162800
(1995)
400 - 420
(1995)
For population <250,000. Based on purchase of building rather than leasing space. Communications includes communications equipment internal to the facility such as equipment racks, multiplexers, modems, etc.
Transit Center HardwareTR001109.0 - 12.0
(2004)
0.18 - 0.24
(2004)
Includes three workstations. O&M estimated at 2% of capital cost.
Transit Center Software, IntegrationTR00220775 - 1636
(2005)
6.0 - 12.0
(1995)
Includes vehicle tracking & scheduling, database & information storage, schedule adjustment software, real time travel information software, and integration. Software is COTS.
Transit Center Additional Building SpaceTR0036.0 - 9.0
(1995)
Additional space required for ITS technology. 500 sq.ft. ($12 to $18 per sq. ft.)
Transit Center LaborTR004100 - 400
(2005)
Labor for one to three staff @ $125K. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.
Upgrade for Auto. Scheduling, Run Cutting, or Fare PaymentTR0052020.0 - 40.0
(1995)
0.4 - 0.8
(1995)
Processor/software upgrade, installation and one year maintenance (for processor). Software is COTS.
Integration for Auto. Scheduling, Run Cutting, or Fare PaymentTR01220214 - 476
(2005)
Integration with other systems.
Further Software Upgrade for E-Fare PaymentTR0132040.0 - 60.0
(1995)
0.8 - 1.2
(1995)
Software upgrade. Software is COTS. Automatic passenger counter processing software costs an additional $25K to several hundred thousand dollars depending on the system.
Vehicle Location InterfaceTR0072010.0 - 15.0
(1995)
Vehicle location interface.
Video Monitors for Security System TR00853.0 - 7.0
(2003)
0.06 - 0.14
(2003)
Five per site. O&M estimated at 2% of capital cost.
Hardware for Security SystemTR0091015.0 - 22.0
(2004)
0.30 - 0.44
(2004)
Includes one server and three workstations. O&M estimated at 2% of capital cost; could be higher for preventative and responsive maintenance.
Integration of Security System with Existing SystemsTR01020250 - 500
(1995)
Integration with other systems.
Labor for Security SystemTR011202 - 247
(1995)
Labor for three staff @ $75K each. Salary cost are fully loaded prices including base salary, overtime, overhead, benefits, etc.