Cost Subsystem
Unit Cost Element
Unit Cost Component
Description
Cost based on physical building cost/ comm infrastructure. This is based on the 12,000 sq.ft. building for Artemis Control Center in Cincinnati. Includes all costs from ground-breaking to ribbon-cutting. Miami also has a 12,000 sq.ft. building that was remodeled for Florida DOT.
Capital Cost Per Unit
$12,000,000.00
OM Cost Per Unit
$60,000.00
Adjusted Capital Cost Per Unit
$12,000,000.00
Adjusted O&M Cost Per Unit
$60,000.00
Lifetime
20
Unit Cost Type
Unit
Lump Sum (LS)
CPI ID
4
CPI Name
NDU BBLD-BBLD
Year
2001